The Future is Bright…

October 2020 Update

The Warwick School is extremely proud to be part of The Priority Schools Building Programme which has enabled us to have a large build on our site.  This is an amazing opportunity for the school and will provide young people with a state of the art facility which will enhance the learning experience for all of our community.  We are very excited by this project but also aware of the need to maintain a high quality education during the next two years. Inevitable there is going to be some disruption during the works but our aim in collaboration with Kier will be to keep this to a minimum.

The end product will be a 4 court sports hall and changing areas, main hall, dining area and library with 9 new classrooms, 8 science labs, 3 specialist DT rooms, a drama studio, 2 ICT rooms and a suite of rooms for students with learning needs.  There are three phases of the project as shown in the timeline below:

January 2019 Contractors arrive on site
  Enabling works for Phase 1 begins
February 2019 Phase 1 starts:  Building of the sports hall
June 2019 Enabling works for Phase 2 begins
August 2019 Phase 1 ends: Completion of the sports hall
September 2019 Phase 2 starts: Building of the main school
January 2021 Phase 2 ends:  School moves into the new building
February 2021 Phase 3 starts: Demolition of existing main teaching block
March 2021 Landscaping
May 2021 Phase 3 ends.

Changes to the School Day from September 2021

Moving Forward

Consultation on the School Day